Tips: Sample PMP Test Question and Answer #8 |
|
Published on Wednesday, July 29, 2009 - 02:46 PM |
Which process is associated with breaking down the project into smaller, more manageable elements?
Answer: C
During project scope definition the details of the project are identified and included in the project scope statement. The scope statement is used as a basis for developing the work breakdown structure which is created through a process known as decomposition. |
 |
Tips: Sample PMP Test Question and Answer #6 |
|
Published on Tuesday, May 26, 2009 - 02:03 PM |
During a software project, you, as the project manager, gather data from the project team and perform an Earned Value Analysis of the project. Your analysis is based on the following information:
EV: 523,000 PV: 623,000 AC: 643,000.
Your Earned value report will indicate which of the following?
- CV: +120,000; SV: +100,000.
- CV: +100,000; SV: +120,000.
- CV: -100,000; SV: -120,000
- CV: -120,000; SV: -100,000.
Answer: D
Cost various is determined by comparing the Earned Value or Budgeted Cost of Work Performed with the Actual Cost ( AC) or Actual Cost of Work Performed. In this case the actual cost is greater than the budgeted cost indicating a negative cost variance or an over budget situation.
© 2009 allPM.com |
 |
Tips: Sample PMP Test Question and Answer #3 |
|
Published on Wednesday, April 22, 2009 - 01:55 PM |
You are the project manager for a project team that is developing a new machine for your company. The machine will produce a specific part used to be used in the assembly of a state of the art robotics product. You are in the testing phase of the project life cycle. The control chart produced during the test indicates 8 consecutive data points above the process average but well below the UCL. How do you interpret the information on the chart?
a) The process is in control and the next phase of testing should begin
b) The chart indicates a run and further analysis is required
c) The data points are within the mean and the UCL and indicate acceptable performance
d) The process average should be re-calculated
Answer = b. A run on a control chart indicates that some specific or special cause may be a factor in the process. A general rule for interpreting control charts is that if seven or more consecutive data points appear on the control chart a “run” has been established and an out of control situation may exist. Further analysis to determine the cause of the run is necessary.
© 2009 allPM.com
More Sample PMP Test Questions. |
 |
Tips: Sample PMP Test Question and Answer #1 |
|
Published on Monday, April 20, 2009 - 02:21 PM |
As the project manager for a newly charted project you have developed the following information based on the input from your project team members: Optimistic time for project completion = 25 weeks, pessimistic time for project completion is 50 weeks, most likely time for project completion is 40 weeks. Using the weighted average technique you have determined that there is a 95% probability that the project will be completed:
a. Between 35 and 43.34 weeks
b. Between 30.83 and 47.51 weeks – correct answer
c. Between 26.66 and 51.61 weeks
d. Between 30.83 and 51.61 weeks
|
Read full article: 'Sample PMP Test Question and Answer #1' (2059 bytes more)  |
|
|
Tip of the day:
Establish an environment where reporting bad news in a timely manner is encouraged rather than an environment where fear prevents the flow of critical information.