The Project charter is an important document and is generally developed after completion of the project selection process. Which of the following is not usually included in the Project Charter?




  1. The formal authorization to apply organizational resources to project activities.

  2. Work package descriptions.

  3. The business need that the project was undertaken to address.

  4. A description of the desired product or deliverable.


Answer: B



The work packages are developed after the project scope statement has been approved and during the decomposition process as the WBS is created. Work package descriptions or other details about the WBS are usually included in a WBS dictionary.